The City of Galt Public Works Dept. has awarded a contract to Knife River Construction for pavement work and minor concrete ramp replacement work. The main construction activities (7am to 4pm) are as follows:

 

From

To

Activity

Estimated Date of Work

Lake Canyon Ave.

Carillion Blvd.

Fermoy Way

Pavement Grinding

8.22.19

Industrial Drive

Live Oak Avenue

Pringle Ave.

Pavement Grinding

8.23.19

Oak Avenue

A Street

Elm Ave.

Pavement Grinding

8.26.19

Oak Avenue

A Street

Elm Ave

Pavement Resurfacing

8.27.19

Industrial Drive

Live Oak Avenue

Pringle Ave.

Pavement Resurfacing

8.28.19

Lake Canyon Ave.

Carillion Blvd.

Fermoy Way

Pavement Resurfacing

09.07.19

 